FOR REGIONAL GAS PIPELINE DEVELOPMENT
Client
An Utilities Provider
Products & Services
- Socio-economic Modelling
- Socio-economic Impact Analysis
- Data Analytics
“Assessing the socio-economic impact arise from the regional gas pipeline development to justify for the CAPEX investment from government”
Description of Project
Client
The client is a government-owned entity and going to undertake the ownership, construction and operations of more than 1,000 km gas and multi-products pipeline.
-
Background
The pipelines are to be built for transporting gas from offshore to fuel 4 new gas power plants, and the other is 600 km multi-product pipeline proposed for the transportation of petroleum products from existing refinery to 3 new proposed distribution terminals.
Challenges & Expectations
In view of the huge capital expenditure, the client would like to commission a study
to assess the viability of the 2 projects by calculating Internal Rate of Return on Investment (IRROI) as well as the benefits to the local communities.
Our Role on the Project
Scope of Services
Our scope was to conduct an Economic Impact Assessment on the benefits of the two projects to the State & Federal government, and the nation as a whole.
Solutions / Outcomes Delivered
- Prepared a 27 year economic impact socio economic model for the Client.
- Assessed the Economic Internal Rate of Return (EIRR) for each project.
- Quantified the contribution in terms of GDP and jobs creation, the Debt to GDP ratio on Malaysia with and without the two projects.
- Presented the economic key indicators for the two projects on overall economic impact to the State government, the Federal government and the nation as a whole.